recent working together on a contract in Burton on Trent for Ivor King Piling on behalf of Galliford Try installing sheet piles for a flood alleviation project. The piles were being installed using the Giken GRB and Super Crush system. Our role was to supply the cranes and some of the ancillary equipment to the project. One of our Sennebogen 680HD 80 tons lattice boom crawler cranes was situated at the start of the pile line and was used for unloading piles from delivery lorries and distributing piles to the Giken TB3 pile runner. Which then delivers the piles down the line of the previously installed piles to the Giken CB2 clamp crane. The clamp crane which also walks along the piles, slews around and pitches the pile into the chuck of the Giken super crush pile the piler. All equipment supplied with experienced operators, available for hire anywhere in the world.

 