RTG RG21T installing cut off wall using SMW triple paddle soil mixing techniques in Leeds

19 Mar 2013, 3:26 PM

RTG RG21T telescopic leader rig with SMW550 triple paddle wet soil mixing equipment on hire installing a soil mixed cut off wall in Leeds for MEL (UK) Ltd to approx 8 m depth through dense gravels and boulders, along with one of our MAT SCA-15 slurry mixing plants.

A total of 130 m of wall has to be treated and so far the machine is making very good progress.